Thursday, November 14, 2024

Flood Recovery Report

Kenmure Country Club

Flood Recovery Report

November 14, 2024

 

Background: On Friday, September 27th, a historic flood impacted the Kenmure Country Club golf course, causing extensive damage across multiple areas. The course partially reopened on October 8th, and by October 11th, it was fully accessible, though temporary greens were in place on holes four and seventeen. The recovery efforts involved a series of structured actions and adaptations as conditions allowed.


 

Initial Assessment and Immediate Response

 

First Survey - September 28th:

  • Upon arrival, silt contamination from Kings Creek was evident, especially in areas like the fourth approach, creating a large, impacted zone.
  • Significant damage was observed at the culvert on hole ten, where erosion created a forty-foot-wide chasm. Further inspections revealed compromised culverts on seventeen, where creek water had diverted across the cart path, and severe silt accumulation covered parts of the seventeenth green.
  • Additional silt contamination was noted on the fairways and approaches for holes four, six, and seven, alongside damage to the cart path near the creek on seven and over thirty downed trees blocking key pathways.

Priorities and Planning:

  • The immediate priority became clearing silt off the greens to prevent turf death, focusing on the seventeenth green as an initial target.
  • With significant obstacles, a multifaceted approach was established to systematically clear routes, remove tree debris, and restore accessibility, allowing regular maintenance to continue in unaffected areas of the course.

 



 

Week One – Two: Beginning Cleanup and Stabilizing Operations

 

Debris Clearing and Path Access:

  • Initial tasks involved small-scale silt removal on cart paths to maintain course access and prevent mud buildup.
  • Additional club employees assisted with minor brush and debris cleanup, creating manageable work zones.
  • By the end of the first week, the primary focus was tree removal, with debris like limbs and brush stacked visibly at the lower parking lot and maintenance area, providing morale-boosting, visible progress.

 


 

Week Three – Four: Intensive Tree Removal and Access Restoration

 

Tree and Debris Clearing:

  • With accessible routes established, focus shifted to removing larger tree debris and stumps, completed by a dedicated outside crew. This milestone marked a turning point, visibly restoring a sense of normalcy and reinforcing the team’s progress for both members and staff.

Silt Removal and Irrigation Challenges:

  • Concurrent with tree clearing, silt removal continued in impacted areas, including the seventeenth green surrounds and fairways on four, six, and seven.
  • Manual irrigation became necessary due to flood-damaged control boxes on holes seventeen and four, limiting water distribution to these zones until repairs could be scheduled.

 

 


 

 

Week Five – Six: Large-Scale Silt Removal and Hydroseeding

 

Restoration of Fairways and Approaches:

  • Specialized crews managed extensive silt removal and reshaping, particularly around seventeen and four. This preparation facilitated reseeding efforts in these critical zones.
  • A skid steer enabled the creation of a central silt disposal site between holes four and seven.

 

Seeding and Favorable Conditions:

  • Hydroseeding began, with bentgrass seeded in fairways and tall fescue in rough areas. Ideal weather conditions—warm days and nights, followed by steady, light rainfall—supported successful germination across these areas.

 


 

Irrigation Repairs and Continued Progress

 

Irrigation and Watering Adjustments:

  • The irrigation system suffered damage, with flooded pump stations and damaged control boxes. Initial manual watering filled the gap until repairs could proceed.
  • A diver inspected the intake in the irrigation pond, while a repair team restored the pump station, returning critical functionality.

Further Seeding and Turf Health:

  • Despite irrigation limitations, consistent rainfall supported germination in reseeded areas. Repairs to control boxes on seventeen and four, expected shortly, will restore automated watering and ease maintenance demands.

 

 


 

Current and Upcoming Infrastructure Projects

 

  1. Cart Path and Culvert Repairs:
    • Hole 7 Cart Path: Repair and repaving of the path is a major upcoming project.
    • Hole 10 Culvert: A new culvert will replace the previous structure, scheduled to start in a few weeks. This aims to reestablish normal traffic flow across the course by the new year.
    • Hole 17 Cart Path and Creek Bank: Stabilization work is planned for the creek bank near the cart path, along with cart path repairs.
    • Hole 12 Underground Culvert: Repairs are needed to prevent ongoing traffic diversions near this path.

 

  1. Irrigation Pond Spillway:
    • The spillway sustained major damage, with a significant wall section currently being reconstructed. Concrete pouring is scheduled to complete this critical structure, addressing water flow and structural integrity.

 


 

Conclusion

While not committing to a specific completion date, recovery efforts have made substantial strides toward restoring Kenmure Country Club to its pre-flood condition. The collaboration between regular staff, outside crews, and supportive partners has been crucial, allowing significant progress in the face of complex challenges. Work on infrastructure, turf recovery, and irrigation continues, with key goals set to enhance both the immediate and long-term resilience of the course.

 

No comments:

Post a Comment